This Holiday Season brought so much joy walking through our new Care Center, seeing how much the residents/elders are enjoying the new space. The
December Construction Update
As I’m writing this, it is once again snowing outside! Winter came too soon for sure. Due to the late fall & early winter, the plan is now to
November Construction Update
Both JMHS and the farmers alike are grateful that the weather has been cooperating with us the past 2 weeks, as the wet start to the fall season was
October Construction Update
The “new” front entrance of the JMHS campus (Hospital, Clinic, Care Center, & Assisted Living) is sure taking on a whole new look now that
September Construction Update
The old Care Center demolition was completed in two weeks. A piece of great news is that none of the demolition went to the landfill! All metal was
August Construction Update
We’ve been in the new Care Center for just over a month now & things are going very well. Of course, there are always processes to work on and
Phase II: Old Care Center Demolition to Begin
Johnson Memorial Health Services is set to begin Phase II of the Capital Construction Project. Demolition of the old Care Center, as well as Asbestos
JMHS Care Center Open House Video
Thank you to everyone who joined us for the Community Open House of the replacement Care Center on Sunday, June 3, 2018. We had more than 450 people
K-Bid Online Auction
JMHS has contracted with K-Bid, an online auction house, regarding the current care center fixtures, furniture and equipment that will not be moving